Indonesia's Java-Bali electricity gains more supply as PLTU Java 7 starts operation

Source: Xinhua| 2019-12-13 23:00:28|Editor: zh
Video PlayerClose
INDONESIA-BANTEN-PLTU JAVA 7-OPERATION-KICK OFF 

Photo taken on Dec. 13, 2019 shows the power plant PLTU Java 7 in Bojonegara subdistrict of Banten province, Indonesia. Unit 1 of Indonesia's coal-fired power plant PLTU Java 7 developed by a consortium of Chinese and Indonesian companies officially kicked off commercial operation on Friday. The PLTU Java 7 power plant is currently operated by PT Shenhua Guohua Pembangkitan Jawa Bali which is a joint venture between China Shenhua Energy Co. Ltd. and PT Pembangkitan Jawa Bali - a subsidiary of Indonesia's state-owned electricity firm Perusahaan Listrik Negara. (Xinhua/Du Yu)

BANTEN, Indonesia, Dec. 13 (Xinhua) -- Unit 1 of Indonesia's coal-fired power plant PLTU Java 7 developed by a consortium of Chinese and Indonesian companies officially kicked off commercial operation on Friday.

Unit 1 of PLTU Java 7 is situated in Banten province's sub-district of Bojonegara. Unit 2 is currently under construction and is expected to commence commercial operations soon.

The PLTU Java 7 power plant is currently operated by PT Shenhua Guohua Pembangkitan Jawa Bali which is a joint venture between China Shenhua Energy Co. Ltd. and PT Pembangkitan Jawa Bali - a subsidiary of Indonesia's state-owned electricity firm Perusahaan Listrik Negara.

"I feel proud of the project because I see PLTU Java 7 is a megaproject with national strategic value. It will reduce the electricity supply cost especially for the Java-Bali electricity," Pembangkitan Jawa Bali's President Director Iwan Agung Firstantara said on Friday at the power plant.

China Shenhua Energy currently has 70 percent stake in the project, while Pembangkitan Jawa Bali has 30 percent.

According to Perusahaan Listrik Negara, the project cost is about 1.8 billion U.S. dollars.

Indonesian President Joko Widodo's administration has been working to reach the target of an additional 35,000 MW electricity supply by the end of 2019.

Chief engineer of Guohua Electric Power Company, China Energy, Chen Yinbiao, told Xinhua on the site that the Chinese engineers in the power plant will share their knowledge and experiences with their Indonesian counterparts to accelerate the adoption of the advanced technology applied in the power plant.